Project
Windfarm and Substation Works
Client
Pacific Hydro, Senvion, SP Ausnet/UGL Limited
Summary
Pacific Hydro: Portland Wind Farm Extension
• GR Carr – 17km turbine access tracks
• 23 hardstands constructed
• Consolidated Power Products – Switchyard Civil Works
Senvion Australia Pty Ltd: Murra Warra Ancillary Wind Farm Works
• 5.7Ha Hardstand construction for turbine equipment staging/laydown area
• Over 30,000m³ of pavement materials imported / placed and compacted
• Total works completed within 6 weeks
SP Ausnet/UGL Limited: Heywood Terminal Station
• Civil Earthworks – Cut and Fill
• Underground Drainage and Sub-Surface Drains
• Concrete Spoon Drain and kerb/Channel
• Class 2 / 3 FCR subbase
• High risk environment and stringent management protocols |